Ferry haul out update – Next dry dock scheduled for 2019
Skagit County has recently issued a Call for Bids for the next scheduled ferry haul out and maintenance period. The bid package allows for the Contractor to propose a 21-day period for the haul out between February 1 and April 1, 2019. The bid documents state that the vessel must be back in service by April 1, 2019.
Bids are due October 8, and we will know exact dates known shortly thereafter. We will send out a notification when we have more information. If you are interested in checking out the bid documents (including specific work items), they are available at https://www.skagitcounty.net/Departments/Rfp/2018haulout.htm.
Sincerely,
Captain Rachel Rowe
Ferry Operations Division Manager
Skagit County Public Works
Anacortes Terminal – 500 I Ave. Anacortes, WA 98221
Source Email 9.28.2019 11:00 AM